A kaizen event is a short, focused improvement project in which a small team from different functions leaves its normal work for three to five days, studies one process where it happens, and changes it before the week is over. It is also called a kaizen blitz, a kaizen workshop or a rapid improvement event.
What sets it apart from an ordinary project is that the changes are made during the event. The team does not hand over a report with recommendations. It moves the equipment, rewrites the standard, tries the new way on the next shift and measures what happened.
What is a kaizen event?
A kaizen event has four features:
- One process, tightly scoped. A changeover on one line, the goods-in area, the discharge process on one ward. Not “quality” or “the warehouse”.
- A measurable goal. Changeover time from 48 to 25 minutes, walking distance halved, queue time under a day.
- A team that includes the people who do the work. Usually six to ten people: operators from the area, a supervisor, maintenance or engineering, someone from the process before and after, and one person from outside who asks the obvious questions.
- Authority to change things that week. The sponsor clears the obstacles in advance, so the team can move a bench or change a schedule without waiting for a committee.
Kaizen means improvement in small steps by everyone, every day. A kaizen event is the concentrated form of the same idea: the same method, the PDCA cycle, run in days instead of months.
What is the difference between a kaizen event and daily kaizen?
| Daily kaizen | Kaizen event | |
|---|---|---|
| Who | Everyone, in their own area | A cross-functional team of six to ten |
| Size of change | Small, within the team’s own control | A whole process, across team boundaries |
| Time | Minutes a day, all year | Three to five full days, plus preparation and follow-up |
| Trigger | A problem or idea someone notices | A gap management has decided to close |
| Risk | Low | Higher: it takes people off the line and raises expectations |
The two feed each other. Daily ideas show where an event is needed, and an event leaves a list of smaller improvements for the area to finish afterwards. A site that only runs events gets a few big jumps and slides back between them. A site that only collects daily ideas never fixes the problems that cross departments.
When should you run a kaizen event, and when not?
A kaizen event fits when:
- The problem crosses team or shift boundaries, so nobody can fix it alone.
- The process can be seen and measured in a few days.
- The fix is mostly about how work is organised: layout, sequence, hand-offs, standards.
- Management is ready to act on the result the same week.
Choose something else when:
- The cause is unknown and needs weeks of data. Use A3 problem solving or a DMAIC project.
- The fix needs capital spending or a new IT system. An event can prepare the case, not deliver it.
- The area is in the middle of a reorganisation or a peak season.
- One person could make the change tomorrow. Then it is a daily improvement, and a week-long event would be theatre.
How do you run a kaizen event? The three phases
Most of the result is decided before and after the event week.
Before: two to four weeks of preparation
- Pick the process and the goal with the sponsor, from a real business gap.
- Write the charter (template below) and agree what is in and out of scope.
- Choose the team and free them completely for the week.
- Collect baseline data: times, volumes, defects, a floor plan, the current standard.
- Tell the area what will happen and why, including the shifts that are not in the team.
- Prepare the practical things: a room near the process, maintenance support on call, materials for marking and moving.
During: a typical five-day agenda
| Day | Focus | What the team does |
|---|---|---|
| 1 | Train and see | Short training in the tools needed. Walk the process, time it, film it, map the current state. |
| 2 | Understand | Analyse the data, find the waste and the causes, agree the target state. |
| 3 | Change | Make the changes: move things, mark the floor, build simple fixtures, write the draft standard. |
| 4 | Test and adjust | Run the new process on real work, measure it, fix what does not hold, train the other shifts. |
| 5 | Standardise and report | Finalise the standard, list the open actions with owners and dates, present the before and after to management at the workplace. |
Many organisations now run three-day events for smaller scopes. The order stays the same: see, understand, change, test, standardise.
After: the 30-day follow-up
The week ends with a list of things that could not be finished, often called the 30-day list or the kaizen newspaper. This is where events most often fail.
- Every open action has one owner and a date within 30 days.
- The sponsor reviews the list weekly at the workplace.
- The team measures the result again after 30, 60 and 90 days.
- The new standard is audited, for example as part of a gemba walk.
- When the numbers hold, the event is closed and the lesson is shared with similar areas.
What goes in a kaizen event charter? A template
| Section | What to write |
|---|---|
| Process and area | Where the event takes place, and where the process starts and ends |
| Problem and background | What is wrong today and why it matters now, with numbers |
| Goal | One to three measurable targets |
| In scope and out of scope | What the team may change, and what it may not |
| Team | Sponsor, facilitator, team leader, members and their roles |
| Dates | Preparation, event week, report-out, 30-day review |
| Baseline data | The measurements the team starts from |
| Constraints | Budget, safety rules, production that must still be delivered |
| Support needed | Maintenance, IT, cover for the people in the team |
One page is enough. If the scope does not fit on one page, it is too wide for one event.
Who does what in a kaizen event?
- The sponsor owns the area or the result. They choose the topic, free the team, remove obstacles and attend the report-out.
- The facilitator knows the method. They plan the week, teach the tools and keep the team on the scope. They do not decide the solution.
- The team leader, often the supervisor of the area, owns the changes afterwards.
- The team members do the observing, the thinking and the physical work. At least half should work in the process every day.
What does a kaizen event look like in practice?
Here is a typical example from a packaging plant, simplified.
Scope: changeover on packaging line 3, from the last good pack of one product to the first good pack of the next. Problem: a changeover takes 48 minutes on average and the line runs six a day, so almost five hours of capacity disappear daily. Goal: 25 minutes within the event week, without more people.
Day 1 and 2: the team films three changeovers and finds that the line stands still for 19 minutes while people fetch tools and parts, and for 11 minutes while they adjust guides by trial and error. Day 3: a tool cart with a fixed place for each tool, parts for the next product staged before the line stops, and marked positions on the guides for each pack size. Day 4: five changeovers with the new method on two shifts, between 21 and 27 minutes. Day 5: a one-page standard with photos, and a 30-day list: quick-release fasteners for two guards, the same marking on lines 1 and 2, training for the night shift.
After 60 days the average is 23 minutes. Most of the gain came from preparing while the line was still running, which is the first lesson of every changeover event.
What are the most common kaizen event mistakes?
- A scope that is too wide. “Reduce waste in the warehouse” cannot be changed in a week.
- A team without the people who do the work. Engineers redesign a job that operators then quietly change back.
- No preparation. The team spends two days finding data that could have been ready on Monday morning.
- Solutions decided in advance. If the manager already knows the answer, the event is only there to sell it.
- No follow-up. Without the 30-day list and an owner, the area is back to the old way within a month.
- Events instead of daily improvement. Events are for the problems daily work cannot reach. They do not replace it.
- Counting events. The number of events held says nothing. The results that still hold after 90 days do.
Where does the kaizen event come from?
The format grew out of the improvement workshops Toyota ran in its own plants and at its suppliers. From the late 1980s, consultants who had worked in Toyota’s production system brought week-long workshops to Western manufacturers, a story James Womack and Daniel Jones tell in Lean Thinking. In the 1990s the Association for Manufacturing Excellence spread the format in the United States under the name Kaizen Blitz. Masaaki Imai, whose 1986 book made the word kaizen known outside Japan, stresses that the workshop is only one part of kaizen and that the everyday part matters more.
How do employee ideas fit into kaizen events?
Employee ideas matter at both ends of an event. Before it, the ideas and problems people report show where an event is worth a week of six people’s time. After it, the 30-day list is a set of small improvements that need an owner, a decision and a visible result.
In Hives, people in the area report problems and suggestions in about two minutes from a phone or a QR code on the wall, also on the shifts that are not in the event team. A collection’s steps can follow the event: suggestions before the week, decisions during it, the open actions afterwards with one person responsible for each. Everyone who contributed can see what was decided and what it gave. That is what keeps ideas coming once the event team has gone back to work. Our guide on how to digitise your kaizen process covers the daily side.
Frequently asked questions
What is a kaizen event?
A kaizen event is a three-to-five-day improvement project in which a cross-functional team studies one process at the workplace and changes it during the event. It ends with a new standard, measured results and a short list of open actions.
How long does a kaizen event take?
The event itself usually takes three to five full days. Count two to four weeks of preparation before it and at least 30 days of follow-up after it.
What is the difference between a kaizen event and a kaizen blitz?
None in practice. Kaizen blitz, kaizen workshop, rapid improvement event and rapid improvement workshop are names for the same format. Kaizen Blitz is the name the Association for Manufacturing Excellence used when it spread the method in the United States in the 1990s.
How many people should take part in a kaizen event?
Six to ten is typical. Fewer than five and the team lacks the functions it needs. More than ten and people start watching instead of working.
What is a kaizen burst?
A kaizen burst is a symbol on a value stream map: a starburst drawn at the point in the flow where an improvement is needed. Each burst is a candidate for a kaizen event or a smaller improvement.
Is a kaizen event the same as a Six Sigma project?
No. A kaizen event takes days and fits problems where the team can see the waste and change the process at once. A Six Sigma project follows DMAIC over months and fits problems where the cause is hidden in variation and needs statistical analysis.
How do you measure the result of a kaizen event?
Against the goal in the charter, using the same measurement before and after: time, distance, defects, stock or space. Measure again after 30, 60 and 90 days to see whether the new standard holds.
Sources
- Masaaki Imai, Gemba Kaizen: A Commonsense Approach to a Continuous Improvement Strategy, McGraw-Hill, 1997
- Anthony C. Laraia, Patricia E. Moody and Robert W. Hall, The Kaizen Blitz: Accelerating Breakthroughs in Productivity and Performance, Wiley, 1999
- James P. Womack and Daniel T. Jones, Lean Thinking: Banish Waste and Create Wealth in Your Corporation, Simon & Schuster, 1996